- 9/20. Define project precisely. How many behaviors per object, how many objects, what behaviors, what variables, how communications will work…
- 10/4. Interactions chosen, Objects chosen and roughly illustrated.
- 10/18. Prototype of objects and interactions ready for initial user testing.
- 11/1. Engineering for networking completed. Robust communications. Draft CAD drawings for objects.
- 11/8. CAD of objects completed. Other engineering done. Ready for final build.
- 11/22. Objects built and mechanically functional. Networking and behavioral patterns roughed in.
- 12/6. Objects work, interact and look as they should. < 1 week of touch-up and debugging is required to make them show-quality.